DRC approves removal of structurally unsafe church bell tower with porte‑cochere replacement, sets design conditions
Summary
The Development Review Committee approved demolition of a structurally compromised church bell tower (236 South Church Street) and replacement with a porte‑cochere after the church reported extensive termite and dry‑rot damage; the committee required the replacement to match arch ratios, eave/rake detailing and to continue the covered‑walkway trim band.
Get email alerts on the Demolition topic
No spam. Unsubscribe anytime.
Amy Wilson, city planner, presented an application to remove the bell tower at 236 South Church Street and replace it with a porte‑cochere. Staff said the structure is a priority‑2 historic resource but that the church’s engineer, Jean Jackson, concluded the tower was substandard and dangerous. The historical commission reviewed the matter and recommended approval of a replacement after determining rehabilitation or reconstruction were not feasible within the church’s budget.
A church representative described progressive termite and dry‑rot damage uncovered during demolition efforts, saying the tower ‘‘was being held up by stucco’’ and explaining that fundraising and grants had not covered the cost of full reconstruction. Committee members questioned whether the remainder of the building had been inspected for similar damage and urged the applicant to consider targeted inspections of like‑aged building fabric.
Design discussion focused on making the replacement porte‑cochere compatible with the existing building. Committee members asked that the archways on the new portico reflect the same ratio of height to width as the building’s existing arcade arches, that eave and rake detailing be consistent with the rest of the church, and that the horizontal trim band from the covered walkway be continued across the new feature.
Amy Wilson moved approval, stating the project would be categorically exempt under CEQA Section 15301, Class 1, and the committee approved the proposal with the discussed conditions. The motion passed by voice vote 4–0.
Next steps: the applicant will submit final drawings for building‑permit review reflecting the required detailing and the city will include conditions in the permit package. Committee members recommended the church consider further inspections of the remaining vintage portions of the building.