Gage County approves special use permit for commercial public assembly building in Rockford Township
Summary
The Gage County Board of Supervisors unanimously adopted Resolution 26-06 to approve Special Use Permit #2026-3 allowing a commercial public assembly building on a tract in the SW¼ NW¼ of Section 24-3-7, Rockford Township, following recommendation from the county Planning & Zoning Commission.
Get email alerts on the Land Use topic
No spam. Unsubscribe anytime.
The Gage County Board of Supervisors on May 27 adopted Resolution No. 26-06 approving Special Use Permit #2026-3 for the placement of a commercial public assembly building on a tract in the southwest quarter of the northwest quarter of Section 24-3-7 in Rockford Township.
The Planning and Zoning Commission held a public hearing on the application on April 23 and recommended approval after considering public input, the board said. During the May 13 supervisor hearing the board heard comments both in support of and opposed to the permit, and those views were considered before the vote.
Supervisor Gary Lytle moved to adopt the resolution and Supervisor Eddie Dorn seconded. Chairman Erich Tiemann presided at the meeting and the roll call vote was Yea: Adams, Clabaugh, Haxby, Tiemann, Lytle, Dorn; Nay: None. The motion carried 6-0 and the special use permit was adopted "for the reasons stated on the record," per the resolution language.
The resolution cites compliance with the Gage County Zoning Regulations. The text before the board noted the tract is in a general agriculture (A1) zoning district, and that placement of the proposed commercial use requires approval via a special use permit under section 5.15 of the county zoning rules.
The board did not record additional conditions in the recorded resolution language; the resolution provides checkboxes for possible conditions and the adopted copy states the permit was approved "for the reasons stated on the record." The county clerk’s filed minutes and the Planning & Zoning record hold the administrative file for the permit.
The board's action completes the county-level land-use approvals; any subsequent local permits or approvals required for construction, occupancy, or event operations were not detailed in the meeting record and are not specified in the transcript.