Rodeo arena seating set for July completion; staff flag funding shortfall and REET 1 as possible cover
Summary
Staff reported the Rodeo Arena Seating Project is scheduled for completion by July 22, 2026, but an unfinished architect change order for over-excavation and structural fill has created a funding shortfall that staff say could be covered with REET 1 funds.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Patti Stacey, a county staff member, presented an updated contractor schedule and a change-order summary for the Rodeo Arena Seating Project and said the work is scheduled to be completed by July 22, 2026, including punch-list items identified during final inspection.
Stacey told commissioners that the project still requires a change order from the architect to address over‑excavation and structural fill. Staff discussed a secured funding shortfall attributable to unsuitable soil conditions and noted that REET 1 funds could be used to cover the excess costs.
No formal board action was recorded at the May 12 meeting; staff will return with finalized change orders and funding recommendations as needed.