Commission awards $127,064 roof contract for 616 North Broadway as part of downtown stabilization

Pittsburg City Commission · March 11, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Commission approved awarding the roof replacement at 616 North Broadway to Ridgeline Roofing (Ridgeline submitted the low responsive bid of $127,064). City staff said total investment in the building will reach about $266,122 after the roof, and the land bank will market the stabilized property for redevelopment.

The commission approved a staff recommendation March 10 to award the complete removal and replacement of the roof at 616 North Broadway to Ridgeline Roofing of Joplin for $127,064, following a competitive bid process with three bidders.

Staff described scope and risk allowances: approximately 2,200 square feet of decking replacement included in the bid, unit prices for additional decking or for parapet capping and wood blocking, and the potential need to replace some truss top chords. The winning bidder proposed a 21‑day construction timeline, which commissioners called aggressive but acceptable if weather permits.

Staff provided a financial summary for the city’s investment in the building: about $349,122 spent to date (engineering, environmental, stabilization), $210,000 committed from a private donor, leaving an estimated city exposure of $139,122 before the roof; adding the $127,064 roof brings the city’s total in cost to about $266,122. The land bank will market the building after work is complete; the land bank board would consider offers and any sale proceeds would be returned to recoup city costs.

The commission approved the award and directed staff to proceed with pre‑construction coordination and documentation, including bonding and unit‑cost oversight.