Summary

District facilities staff reported progress at the new Southern Gap High School: football bleachers are installed, turf prep is underway, drywall and flooring work are near completion and kitchen and science classroom installations are in progress; administrators said sidewalks, fencing and final punchlist items remain.

District facilities staff presented a progress update on the new Southern Gap High School, showing photos and listing remaining work items as construction moves toward completion.

The update noted that football bleachers are installed and crews have started preparation for turf installation; sidewalk pours, fencing and final field prep remain on the schedule. Inside the building, drywall and ceilings are nearing completion and the third‑ and second‑floor wing flooring is substantially finished. Kitchen equipment and family consumer science equipment are being installed, and casework and counters are in progress in science classrooms.

Facilities staff said gym sub‑floor work has started and that crews will install the maple hardwood surface once sleepers and plywood are in place. The band room will receive ceiling and sound panels before final commissioning. For the nursing wing, remaining work items include hanging doors and installing window sills.

Board members asked about finishes and exterior work, and staff reiterated the need to complete asphalt, sidewalks and fence installation before the turf and fields can be put in service.

Why it matters: The new school’s progress affects student transitions, athletic scheduling and the district’s opening logistics for Southern Gap High School. The board authorized opening an interim bank account so the school can begin limited financial operations ahead of full opening.

Next steps: Facilities will continue scheduled work on turf, fencing and interior finishes; administration will finalize room assignments and open a bank account to allow initial, limited transactions before the school opens.