Developers ask Montgomery to amend Crossing at Town Center agreement to speed utilities; council to review escrow and road protections
Summary
Developers updated the council on the 235‑lot Crossing at Town Center, proposing that the developer’s engineer complete the on-site lift station while the city finishes offsite force main work to save six to nine months; council asked staff and legal to draft possible amendments, escrow terms and road-protection language.
Get email alerts on the Development Agreement topic
No spam. Unsubscribe anytime.
Developers and city staff told the council they want to amend the 2024 development agreement for the Crossing at Town Center to change which engineer completes certain utilities, a revision developers said could speed delivery of lots.
Staff recapped that the development originally included a city-contracted engineer for offsite utilities and that the developer asked for changes so their engineer would construct the lift station while the city's engineer finishes offsite force main and sewer extensions. The developer said that approach is used elsewhere and that splitting responsibilities could save roughly six to nine months and reduce upfront cash-flow burdens by allowing costs to be paid monthly rather than as a single large lump sum.
Councilors and staff discussed escrow deposits, providing pre-construction photos to protect city roads from construction damage, explicit construction-access language in amended agreements, and the process for reviewing audited contractor costs before allowing subsequent sections to proceed. Staff noted the development covers about 235 lots and that earlier feasibility and annexation work had already been done.
No amendment was adopted on May 26; staff will compile comments, consult legal counsel, request additional escrow from the developer for amendment processing, and return with a draft amendment and recommended protections (including road repair and pre-construction documentation) for council consideration at a future meeting.