Council approves $125,000 change order for ice-rink systems; staff to seek contractor responsibility
Summary
The council authorized a change order with Icebuilders Inc. that increases the ice-rink systems contract by an estimated $125,000; councilmembers said staff and legal counsel will pursue responsibility with prior contractors and review compaction testing.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
During the consent agenda the East Brunswick Township Council considered Resolution 25-262, authorizing Change Order No. 1 with Icebuilders Incorporated for the township's ice-rink systems project. Council discussion identified an estimated cost increase of $125,000 tied to additional excavation, recompaction or fill in one rink area.
Council members said the town will investigate whether Legacy Place (the pad contractor) or the general contractor Terminal Construction share responsibility and whether third-party compaction testing was completed before turnover. "We are going to continue our research on this and try to get a full understanding as to where the responsibility lies," one council member said, and legal counsel was reported to be placing relevant parties on notice.
Council did not halt the work; members said the work needed to proceed but that the township will pursue reimbursement where appropriate and continue due-diligence steps. The council approved the consent-agenda resolution authorizing the change order as presented.