Marshall council authorizes purchase of shade shelter for new aquatic park

Marshall City Council · May 26, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The council approved purchase of a vented 16x20 shade shelter for the new Marshall Aquatic Park under state contract pricing (purchase and shipping about $29,073), with estimated assembly and footings of roughly $15,000 and total project-related costs estimated around $55,000.

The Marshall City Council approved staff's request to purchase a shade shelter for the new Marshall Aquatic Park.

Parks Department staff member Preston Stensrud told the council the shelter would sit outside the pool fence near a newly purchased playground and that the supplier, St. Croix Recreation, holds state contract pricing. "It's about an 18 to 20 week lead time on a shelter," Stensrud said. He described the proposed shelter as a vented-roof unit roughly 16 by 20 feet; purchase and shipping were listed around $29,073, and Stensrud estimated local assembly and footings at about $15,000, yielding a rough total project estimate in the $40,000–$55,000 range once installation and related work are included.

Stensrud said the project fits within existing contingency and sponsorship funding; council members noted constituent interest in shelters during prior playground purchases. Council moved, seconded and approved the purchase by voice vote.

What happens next: Staff will take color samples, finalize procurement, coordinate footing pour with pool concrete work and schedule installation once the shelter is delivered and weather permits.