Republic representative updates committee on new cell, gas-well work and a planned flare
Summary
A presenter representing the landfill operations reported work on Cell 6C, installation of roughly 45 new gas wells and 7,000–8,000 feet of header pipe, plans for a new flare next year and continued leachate hauling to Salem under contract; members asked technical and timing questions.
Get email alerts on the Infrastructure Operations topic
No spam. Unsubscribe anytime.
A presenter for the landfill operations briefed the Benton County Disposal Site Advisory Committee on recent on-site activity and near-term infrastructure plans. The presenter said work has begun on Cell 6C (quarry area), liners and a ‘‘10-foot fluff’’ intermediate cover to protect liners during construction, and that crews have been stripping tarps and finishing sliver-fill work on the top deck.
On landfill gas infrastructure, the presenter reported the owner began gas-construction late last month and ‘‘we’re putting in 45 new wells’’ plus roughly ‘‘7,000, 8,000 feet of new header pipe’’ and additional well piping as they target gaps or replace collapsed wells. The presenter said some wells are redrills near collapsed or deviated wells and that the program will target west-then-east phases over the coming months.
The owner is preparing a new flare and related infrastructure, the presenter said. ‘‘We’re putting a new flare in next year’’ and are designing to achieve the required destruction efficiency for non-methane organic compounds; the presenter said flare operation aims for high destruction efficiency (discussed as 90–98% in meeting exchanges).
Leachate: the presenter said leachate hauling currently goes to the City of Salem under an existing contract and that hauling will continue; committee members asked about where leachate and biosolids are disposed and whether local acceptance is changing.
Committee members asked about the wells’ purpose (gas extraction and leachate pumping), spacing, timing and how the work will affect odors and operations; the presenter committed to follow-up where details were not immediately available.
What’s next: the presenter said construction and well installation will continue and staff will provide additional detail for quarterly reporting; committee members requested comparisons to historical quarterly tonnage and clarification on first-quarter tonnage declines.