District outlines modernization timeline and upcoming ribbon cuttings; $3.8M in reimbursements expected

Los Banos Unified School District Board of Trustees · May 14, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Facilities staff briefed the board on multiple modernization projects: Early Education Center ribbon-cutting May 21, Bolta Elementary ribbon-cutting May 28, LBHS attendance office delivery, Pacheco baseball-field bid opening May 20, and $3.8 million expected in reimbursements tied to an EV/solar project.

Facilities staff provided a detailed May update on district construction and modernization projects.

Key dates include a ribbon-cutting for the Early Education Center scheduled for May 21 and a Bolta Elementary modernization ribbon-cutting on May 28. Staff noted furniture deliveries and final commissioning work at Bolta, with outstanding items including reception-window glass and EV-charger commissioning.

At Las Banos High School, the attendance office modular unit was crane-delivered and assembled the same day; locker-room demolition and abatement work are underway. Facilities shared a master schedule showing sequencing through summer and into December, with final cleaning for a new administration building (Building L) targeted for July 31.

Staff announced the Pacheco High School baseball-field bid opening on May 20; if awarded, the project is a 90-day scope. The district also reported it has requested $3.8 million in reimbursements from the San Joaquin Valley Air Pollution Control District for solar/EV projects.

Grasslands Elementary special-education building design is in progress and the district sought authorization to seek bids for a building manufacturer; the board approved that authorization and awarded two LEAP portables to AMS with contract-execution authority delegated to the superintendent.

Trustees asked to receive more-detailed schedules and were assured staff will provide follow-up reports.