Aitkin school board reviews Rippleside repair, remodel and condemnation options as levy, safety needs loom
Summary
Board members discussed urgent repairs at Rippleside, community proposals to remodel the elementary school, and—at the PLC's request—an exploratory look at whether state rules on condemnation might apply. Consultants said condemnation was not recommended; the board directed the project oversight committee to return detailed cost and levy options in June.
Get email alerts on the Facilities Rippleside topic
No spam. Unsubscribe anytime.
The AITKIN PUBLIC SCHOOL DISTRICT board spent a substantial portion of its meeting discussing the condition of Rippleside elementary and how to pay for urgent repairs and longer-term work.
Resident Jennifer Cummings opened public comment by saying she had heard community concerns that the district might pursue condemnation of Rippleside and asked, “Is this something that is seriously being considered?” She also said a public-record summary showed roughly $2.7 million raised by the 2021 levy to date, and that “only 10% has been spent on buildings” while about 70% was listed under technology, a breakdown she said residents wanted explained.
Board members and staff described multiple, overlapping needs: roofs beyond life expectancy, indoor-air-quality and ventilation reviews, asbestos tile abatement in some elementary corridors, septic and general deferred-maintenance work. Consultants from the district’s project oversight process have flagged urgent repairs that cannot wait for a large capital campaign.
Board packet materials cited two high-level cost estimates the board has previously reviewed: replacing Rippleside at the current site at about $49.8 million, and renovating and repairing at roughly $25.5 million. Members emphasized those figures are preliminary and do not capture the immediate urgent fixes the district also must address.
A group of community volunteers submitted an alternate plan that would remodel Rippleside, add roughly five classrooms in a back wing, create a secure entry and consider privatizing bussing. Board members said the community proposal overlaps with work the architects and consultants already have under consideration, but noted the volunteer plan did not address some of the most urgent items—roofs, septic or indoor-air-quality problems.
Several trustees said the idea of condemnation—which a board member noted can arise under Minnesota law when repairs exceed a threshold of a property’s value—had been raised for study by the PLC. Board members repeatedly described that option as an exploratory question rather than a recommendation: consultants did not advise immediate condemnation and the district’s staff said they were not moving forward with such a plan.
The board noted it has limited levy authority without a referendum—approximately $11 million was cited as the amount the board could levy without a community vote—and that any broader replacement or large remodel likely would require a public referendum. Trustees asked staff and consultants for narrower, prioritized cost breakdowns so the board could identify which urgent items warranted immediate action and which might be staged or included in future referendum planning.
Next steps: the district’s Project Oversight Committee will meet May 26 and June 8 and return more detailed budget numbers and consultant contract language to the board for the June meeting. The board also scheduled a possible pre-meeting work session to review those materials before making levy or referendum decisions.
The board did not take a final vote on a construction plan or a referendum; it approved procedural items and directed staff to return with more detailed figures at future meetings.