Board approves Crossings at Cocalico Phase 1 final plan with sidewalk language to mirror preliminary conditions

East Cocalico Township Board of Supervisors · October 2, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board adopted Resolution 2025-25 approving the Crossings at Cocalico Phase 1 final land-development plan (42 units) subject to engineer and solicitor proofing to ensure sidewalk and waiver language match the preliminary-plan conditions; board declined to grant a fee-in-lieu waiver at this time and emphasized pursuing easements and developer cooperation for sidewalk construction.

The East Cocalico Township Board of Supervisors voted Oct. 2 to adopt Resolution 2025-25, granting final-plan approval for the Crossings at Cocalico Phase 1 land-development plan while conditioning the approval on the township engineer and solicitor proofing the resolution to ensure the final document carries forward the preliminary-plan sidewalk and waiver language word for word.

Township staff (Mike) summarized the proposal as a phase-one final plan for 42 housing units — a mix of single-family, duplex and townhouse units — located on the east side of State Route 897 (West Sparksville Road) in the township’s suburban residential zoning district using the village overlay concept. The planning commission had recommended final-plan approval contingent on the conditions now in the resolution.

Discussion centered on a sidewalk requirement on the west side of West Sparksville Road north of Weaver’s Market. The developer’s representatives (identified in the meeting as Elliot and Brandon of Garmin/affiliated team) requested that, if the township could not secure easements from adjacent property owners, the township accept a payment or escrow contribution in lieu of immediate construction so the sidewalk could be built later. Township counsel and the engineer noted that the preliminary-plan approval had included waivers and deferrals and that the final-plan resolution’s language should exactly reflect those prior conditions rather than introduce modified waiver language.

Several supervisors stressed safety concerns for pedestrians, particularly children who might access a nearby park and Weaver’s Market, and urged further staff effort to obtain easements through direct outreach. The solicitor and engineer recommended not exercising any fee-in-lieu waiver at this stage; instead, they recommended the developer and township continue to exhaust options to construct the sidewalk during phase one construction and, only if unavoidable, use a defined escrow or fee tied to actual construction costs (including bidding and prevailing-wage assumptions).

A motion to adopt Resolution 2025-25 as presented, conditioned on the solicitor and engineer proofing the final document to ensure consistency with the preliminary-plan conditions, passed unanimously.

The board also briefly discussed potential grant opportunities; the developer offered to forward grant-application materials to township staff for review. The resolution approval authorizes final plan recording subject to ministerial corrections and the proofing noted in the motion.