Engineer David Powers: $759,038 change order will reintroduce six streets into Clayton water‑main project

Village Board of Clayton · April 2, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Engineer David Powers told the board Change Order No.1 will add 15 previously pulled bid items — restoring work on six streets — and increase the water‑main contract by $759,038; staff said the contractor held unit prices and the board will address the formal vote at the next meeting.

Engineer David Powers told the village board that most of the in‑water intake work for the water project was completed last fall and crews plan to return in spring to complete the connection and bypass work.

"So this change order is for $759,038," David Powers said, describing 15 additive bid items that reinstate work in six areas (Cloverrise Lane, Northshore Drive, Southshore Drive, Sherman and Emery A, and Campbell Drive). He said those areas had been pulled from the original award during bidding to fit earlier bonding limits and are now being reintroduced because the village increased bonding capacity.

Powers said the contractor has been mobilized: "They're on site, they're mobilized. Their equipment's here. Pipe is arriving," and staff expect a stored‑materials payout to be processed in the coming weeks. He added that the contractor was offered the opportunity to re‑evaluate unit prices but "they held their prices for us."

Board members acknowledged they had not all received the change‑order paperwork. Staff did not ask the board to vote on the change order that night; trustees directed staff to circulate the documents ahead of the next meeting so the board could consider formal action.

Why it matters: reintroducing the additive items restores portions of the original project scope without rebidding and allows the village to avoid delaying the contract award while bonding capacity was adjusted. The change order would increase the contract amount and obligate additional funds when formally approved.

Next steps: staff will resend the change‑order documents to trustees and place the item on the next meeting agenda for formal consideration and vote.