Summary

Council members questioned a proposal to add a full‑time public works director — projected at roughly $224,000–$262,000 in salary and benefits — and asked staff for project schedules and cost comparisons before deciding; the item was pulled for later return.

The Grand Terrace City Council on Nov. 9 debated whether to recruit and fund a full‑time public works director, ultimately agreeing to remove the item from the consent calendar and ask staff for more detail.

Council Member Brown pressed staff for measurable justification for adding the position, noting the top salary estimate in the staff report and asking, "If this tops out at nearly $300,000 a year, why are we hiring a permanent director now?" Brown said the council needed a clearer accounting of project delays, budget impacts and alternatives such as hiring a lower‑level manager.

City Manager Conrad responded that the city faces a cluster of complex projects — including a storm drain master plan, a Linton street project with a missing storm drain upsizing issue, the Lewis development and other paving and gateway work — that require a single staff member to manage consultants and contractors. "We will not use fewer consultants," Conrad said. "This is to manage the consultants we have." He added the current part‑time public works director can no longer keep up with the workload and that waiting to hire will risk compounding planning mistakes.

The staff report cited an estimated salary and benefit range of $224,000 to $262,000 annually; it also identified approximately $100,000 in recurring savings from discontinuing a contracted senior civil engineering service and noted a net savings figure in the staff discussion of roughly $62,000 relative to prior consultant costs. Council members asked for a clearer breakdown of those numbers, documentation of delays or project impacts to date, and a Gantt‑style schedule showing near‑term benchmarks so the council can evaluate timing and urgency.

Council members suggested alternatives, including a lower‑cost management analyst or public works manager to oversee consultant work. Several members said they supported strengthening project management but wanted the item returned as a regular agenda item with a scope of work, recruitment plan and comparative cost analysis.

The council did not vote to authorize the hire; members agreed to bring the item back at a future date (midyear or next budget cycle) with additional information and benchmarking.