Staff seeks board sign‑off to prepare change orders for Lascelles Landing comfort station
Summary
Town staff asked the board to prepare resolutions to amend two awarded contracts for the Lascelles Landing comfort station to add remote door access, extra conduits for data/site lighting and other scope items; staff characterized the requests as out‑of‑scope change orders and said the project is largely grant‑funded (noting a $675,000 grant) and at a critical underground‑work stage.
Get email alerts on the Parks Infrastructure topic
No spam. Unsubscribe anytime.
Town staff asked the Penfield Town Board on May 20 to authorize preparation of change‑order resolutions to expand the scope of the Lascelles Landing comfort station contract. Staff said the additions include two spare conduits to the right of way and additional conduits east and west for future data, security and lighting, remote door access controls to enable automated opening/locking and the infrastructure to support future cameras and remote monitoring.
Staff noted these items were requested after the contracts were awarded and therefore fall outside the original contract scope; they recommended treating the work as change orders and asked the board to have resolutions ready to avoid delaying critical underground and foundation work. Staff said there would be no additional cost for one EC‑05 line item (day automation) but that other items would require amending the GC and electrical contracts; staff said roughly $675,000 of the project cost is grant funded and that some change‑order line items total in the tens of thousands.
Board members pressed staff for contingency amounts, asked whether the changes require rebidding (staff said extensions/expansions to existing contracts do not require rebid under the current thresholds and that the town attorney would confirm legal requirements), and directed staff to prepare the resolutions so the board could act at a special legislative session if needed.
Next steps: staff will prepare change‑order resolutions amending the general contractor and electrical contracts and provide contingency details and legal confirmation for the board’s consideration at the next meeting or a specially scheduled legislative session.