Summary

The board heard an update that phase‑two HVAC work at the high school is nearly complete and approved a $96,428 contract with SIC Midwest to repair the Butterfield Early Childhood roof with a 20‑year warranty.

Marshall Public Schools administrators told the board the high‑school phase‑two HVAC installation is nearly complete and the district recommended awarding a Butterfield Early Childhood roof contract to SIC Midwest for $96,428.

Deputy Superintendent Rinke said nine HVAC units were installed through Navitas and that the crew completed major lifts during spring break; final touches were expected to wrap up by the end of the week. "Everything went very smooth," Rinke said, praising director of maintenance Chris Bethel for coordinating with contractors.

Rinke recommended awarding the Butterfield roof work to SIC Midwest for $96,428, describing the scope as a 60‑mil membrane liner with heat‑welded seams and skylight capping, and noting the bid includes a 20‑year warranty. He said the district plans to use leftover construction funds for the project.

Board members discussed bid variance and product longevity, and by voice vote approved the recommended contractor so work can proceed as summer begins.