Board members reviewed FY2026 projections for the Transfer Station, which showed a projected $73,000 shortfall; the Board voted unanimously to seek a $50,000 transfer from the general fund for FY2027 and have $50,000 listed in Article E to come from retained earnings.

The Board reviewed updated year-to-date and FY2027 transfer-station budgets and projected a FY2026 loss of about $73,000, given projected revenue of $465,000 against budgeted expenses of $542,000. Tom Holder and George Uveges said a $50,000 transfer from the general fund and about $24,000 from retained earnings would allow the Transfer Station to break even for FY2026.

For FY2027 the board discussed an anticipated revenue reduction of about $100,000 driven by decreased bag sales and higher vehicle repair costs. Michael Wegerbauer moved that $50,000 be transferred from the general fund for FY2027 and that $50,000 be listed in Article E to be taken from retained earnings; Ed Chiang seconded. The roll-call vote was 5–0–0 in favor (Wegerbauer, Spelman, Chiang, Ling, Uveges all aye).

Joe Doucette provided an update on a consultant selection process: proposals have been received and the working group needs to meet to review them; the scope and timing of the analysis remain unclear but will be relevant to future rate-setting.

The board asked staff to include a cost analysis showing the town cost if Transfer Station operations were terminated for inclusion with any funding motion.