Mount Kisco presents $500K–$1.5M plan to stabilize Leonard Park streambed; culvert and road work slated for 2025
Summary
Village Manager Edward Brancati shared drawings for a streambed erosion project with an estimated cost of $500,000 to $1.5 million, noting the need to secure grants or loans, planned boulder placement and plantings, and a timeline that places culvert and road work in Fall 2025 and streambed/plantings in Spring 2026.
Get email alerts on the Streambed Project topic
No spam. Unsubscribe anytime.
Village Manager Edward Brancati presented drawings and an overview of a multi-phase streambed erosion project for Leonard Park that the village says will address bank instability and recurring flooding.
Brancati said the project estimate is between $500,000 and $1.5 million and that funds must be secured through a grant or loan. The plan calls for placing boulders in areas where the bank cannot be cut back, establishing plantings along the banks, and preparing mowing procedures for the Department of Public Works (DPW) to avoid damaging plantings. Brancati also identified the need to replace a culvert and bridge and to raise part of the adjacent road to address flooding; he described the culvert and road work as separate funding projects that will likely be completed along with the streambed work.
Brancati gave a project timeline: culvert and road work targeted to start in Fall 2025, with streambed stabilization and plantings in Spring 2026, subject to securing funds and completing a bidding process. During open discussion Chairperson Erin Heaton asked whether state representative Chris Burdick might reallocate funds to the streambed project; Brancati said the budget and paperwork for that project have already been submitted.
Why it matters: the work is intended to reduce flooding and improve streambank stability in Leonard Park; if funded and delivered it will affect park access and nearby roadways.
Next steps: village staff will pursue funding options and return with bid documents and further cost details when available.