Fernandina Beach authorizes applications for up to roughly $15–24 million in wastewater and reuse grants
Summary
City staff told commissioners it will apply for two Florida grants related to wastewater and reuse planning and implementation under SB 64: an alternative water supply/reuse grant ($7–9 million) and a water-quality/advanced-treatment planning grant ($14–15 million). The commission approved the authorization unanimously.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Fernandina Beach officials authorized staff to pursue two state grant opportunities aimed at upgrading wastewater-treatment infrastructure and creating a non-potable reuse distribution system required under Florida Senate Bill 64.
Utilities Director Andre Desile told the commission the grants would support a planned wastewater-plant upgrade and implementation of a reuse distribution system to meet a 2032 state goal of eliminating surface-water discharge of treatment plant effluent. Consultants from Woodard & Curran explained the grants' scope: the alternative water supply/reuse-distribution grant was estimated at about $7–9 million, and the water-quality planning grant (focused on feasibility and pre-construction work for advanced wastewater treatment) was estimated at $14–15 million.
"When we were first looking at that grant ... there was a recommendation to go to an advanced wastewater treatment facility," consultant Ryan Watson said, describing the water-quality grant as an opportunity to fund pre-construction planning and feasibility to prepare for potential future regulatory requirements.
Commissioners asked about fees for the consultant's work on the applications; staff said the not-to-exceed fees were $6,000 for one application and $21,000 for the financial/initiative plan associated with the other application. Staff also noted both grant application deadlines fall on June 30 and said they expected to meet that deadline. The commission voted 5-0 to authorize staff to prepare and submit the applications.
If awarded, the grants would be applied to engineering, planning and capital work associated with wastewater improvements and reuse distribution; staff emphasized that applying does not obligate the city to accept a grant if awarded.