Summary

Palmer Associates told the Southside Fire Station Building Committee April 28 that Open Cape will provide redundant fiber service and that sub-bids are due May 6 with GC bids due May 20; the committee unanimously approved two consultant invoices and set the next meeting for May 26 (June meeting moved to June 30).

Christopher George of Palmer Associates gave the committee a project update and a timetable for the Southside Fire Station project, saying the project team is in the bidding phase and working to keep the schedule on track.

"I'm Christopher George, Palmer Associates. I work with Rick on this project," George told the committee, and said the team recently met with Open Cape to plan fiber optics for the site. "They are looking for a redundant system also, so you guys don't have a backup like you had when we had the storm," he said, describing a plan intended to prevent outages during severe weather.

The most immediate procurement milestones: specialty/sub-bids were released April 15 and are due May 6; general-contractor bids are due May 20. George said all bidders were pre-qualified to speed evaluation and that Pomeroy (the owner's representative noted in the documents) will verify bids and present the lowest qualified bidder at the committee's May meeting. He cautioned that "nothing is awarded" until the GC award is finalized.

George introduced Document 3 — the FFN, a furniture, furnishings and equipment tracker — saying the team will bring the owner-item list to each meeting so purchases (desks, chairs, coffee makers and other small equipment) are coordinated before the building opens.

On finances, George said there were no budget movements this month. He presented an invoice summary and the committee took roll-call votes on two consultant invoices. The committee approved an invoice from Sosio Associates (invoice 22085-22, dated April 21, 2026) on a motion from the chief and a second from Peter Lindberg; the roll call recorded unanimous approval. The committee likewise approved an invoice from Pomeroy Associates (invoice 22.107.0-20) for $8,620; that vote also passed unanimously.

Votes at a glance

- Sosio Associates, invoice 22085-22 (April 21, 2026): motion by the chief; second by Peter Lindberg; outcome — approved by unanimous roll call. - Pomeroy Associates, invoice 22.107.0-20: motion moved and seconded; amount read as $8,620; outcome — approved by unanimous roll call. - Minutes (March 3, 2026): approved unanimously; March 24 minutes deferred for proper posting.

What it means

Committee members will review returned sub-bids on May 6 and expect GC bids on May 20; the team's stated approach is to examine the lowest three bids and confirm that the lowest bidder is qualified under state procurement rules before recommending an award. The FFN will be updated monthly to guide owner purchases ahead of construction completion.

The committee scheduled its next meeting for May 26 and moved the June meeting to June 30. The chair adjourned the session at 3:19 p.m.