Monument council awards $1.59M Beacon Light Road water‑main contract
Summary
Council approved a $1,588,920 construction contract with Capital Paving and Construction LLC to replace decades‑old water mains on Beacon Light Road, add service connections and hydrants, and coordinate with county road work; council added contract‑amount language and approved the resolution 6–0.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
The Monument Town Council voted Nov. 17 to award a construction contract for water‑main replacement on Beacon Light Road to Capital Paving and Construction LLC, with staff presenting a contract amount of $1,588,920 and an exercise‑level contingency for planning.
Mr. Thornish, the staff project lead, described the scope as replacement of aging (roughly 40‑year‑old) 8‑inch and 12‑inch mains, new service laterals to roughly a dozen to two dozen properties, installation of new hydrants and coordination with adjacent county road work that will alter road grades. “We made a decision … to put brand new water mains in since what’s existing there has been in the road at least 40 years,” Mr. Thornish said, explaining the choice to install new mains under the rebuilt roadway to avoid premature future breaks.
Nut graf: The contract funds water‑system capital work that staff said is already budgeted in the water fund and tied to the town’s 2026 capital program; council requested that the resolution text be amended to include the explicit contract amount and approved the measure 6–0.
Staff explained the procurement approach and said the contractor’s proposal aligned with the engineer’s estimate; the contract includes language that any change order exceeding 5 percent or $25,000 must return to council for approval. Council members asked for future similar large procurements to be removed from consent agendas so the public can hear discussion; staff agreed.
The presentation also addressed the town’s aging Monument Hill tank and other pipeline tie‑ins: staff said the tank is holding but exhibits deterioration and that tank replacement work is advancing through geotechnical and legal stages.
The council approved the contract with the requested edit to the resolution to state the award amount and instructions for execution; the public hearing was not required for this action.