Select Board weighs near-term heat-pump fix for Mystic School; members ask School Committee to weigh in
Summary
Consultants proposed isolating a corroded 100-year steam core and installing heat pumps to protect programs and avoid catastrophic heating failure. Staff framed a ~ $900,000 near-term option to cover the most at-risk portion of the building; board members asked the School Committee to confirm priorities before allocating ARPA funds.
Get email alerts on the School Infrastructure topic
No spam. Unsubscribe anytime.
Town consultants and staff presented updated designs and cost estimates on June 3 for heating and partial electrification of Mystic School, focusing on isolating a corroded 100-year-old steam piping core and installing heat-pump equipment for the most at-risk areas. The plan offers two equipment approaches โ individual split units or a variable-refrigerant-flow (VRF) system โ and includes electrical upgrade considerations, abatement for asbestos and construction sequencing to minimize disruption to ongoing programs.
Pete (project lead) summarized the proposal: "What this project does is it takes the core of the building which is the 100-year-old portion... replaces the heat source and adds air conditioning to these classrooms by electrification." Consultants said a fully comprehensive replacement of the school-wide system could be a multimillion-dollar undertaking; staff presented a focused option that would address roughly half the building and reduce near-term risk. Town staff noted the design was crafted to fit within roughly a $900,000 budget envelope after anticipated rebates and to avoid a larger service upgrade that would substantially raise costs.
Board members debated whether to spend ARPA funds now on the focused project or to delay and pursue a longer-term capital solution. One select board member characterized the risk as "catastrophic" for many families if the building loses heat and programs must close. Staff said the proposal would buy a several-year window of reliability (estimated 5 years) while the town and the School Committee evaluate longer-term options.
The board agreed the School Committee (tenant for some programs) should be formally consulted before final approval. Staff said they would coordinate a meeting with School Committee leaders and return to the board with any adjustments and a recommended authorization timeline.