Council awards $4M+ reconstruction contract for Timber Valley Drive and Fairfield Lane

Flower Mound Town Council · June 1, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved a construction agreement with DDM Construction to rebuild Timber Valley Drive and Fairfield Lane, citing 50-year-old infrastructure, extensive sub-surface work, new sidewalks/ramps, and a roughly 400-day schedule; staff said 15 qualified bidders responded.

Capital Improvement Programs Manager David Brockway presented the Timber Valley Drive and Fairfield Lane reconstruction project and recommended awarding the contract to DDM Construction. Brockway explained the neighborhood's aging infrastructure, the scope and cost drivers, and the plan to meet with residents about impacts during a roughly year-long construction schedule.

—This is a neighborhood that was built in the late seventies ... 50 year old infrastructure and it shows when you get to this point, it's time to rebuild,— Brockway said, describing 3,600 feet of concrete and base material, new sidewalks and ramps, 4,500 feet of water main and 3,500 feet of sanitary sewer.

Staff reported a strong procurement response (15 qualified bidders) and said the work will include significant subsurface repairs to improve longevity. Council moved, seconded and approved the award by unanimous roll call.

Why it matters: the project replaces failing roadway and underground utilities in a residential area and is funded through the town's capital program; the work will affect adjacent residents during construction but is intended to extend pavement life substantially.

Next steps: staff will schedule neighborhood meetings and begin construction this summer with an estimated 400-day completion timeline.