Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Town advances $750,000 paving bond and approves Veterans Park change order increasing project costs
Summary
Board authorized a $750,000 bond process for the 2026 paving program covering 1.6 miles of town roads and one mile of Staley Road and approved a roughly $67,000 change order for Veterans Park site work after engineers reported unforeseen conditions.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
The Grand Island Town Board on June 1 authorized the supervisor to begin the bond-authorization process for $750,000 to fund the 2026 paving program and approved a change order to the Veterans Park access improvements after engineers reported additional site work and material quantity differences.
Highway staff described the paving program as including mill-and-fill of 1.6 miles of town roads and a one-mile mill-and-fill on Staley Road with shoulder widening and drainage work. The funding breakdown discussed in the meeting allocated approximately $300,000 to miscellaneous town roads and $450,000 to the Staley Road segment. The motion authorized the bond process to proceed.
Engineering staff reported unanticipated site conditions at Veterans Park — including survey-services needs, additional piping and surface drainage work and an underestimated pathway subbase — producing an extra bill of change-order items that cumulatively were cited in the meeting at roughly $67,000. Board members expressed frustration at repeated change orders but approved the additional work to keep the project moving.
Both measures passed in roll-call votes recorded in the transcript; staff said the Veterans Park work was engineered and that the change order arose from on-site conditions rather than a deliberate scope change.
Next steps: the town will initiate the bond process and proceed with the Veterans Park construction work with the approved change order; staff and finance officers will track the additional borrowing and project budget implications.

