Peoria Heights moves forward on major water projects: filtration bid and raw-water main design

Village of Peoria Heights Board of Trustees · June 2, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Trustees authorized notice of intent to award a $6.819 million manganese filtration project and approved $76,000 for design/oversight of a Galina Road raw-water main replacement funded in part by a nearly $990,000 congressional grant.

The Peoria Heights Village Board on Tuesday advanced two substantial water-infrastructure efforts: it accepted a staff recommendation naming Linder Construction as the apparent low bidder for a manganese filtration-plant addition and approved a design-and-construction-services proposal to replace a raw water main from Route 29 to the water treatment plant.

Trustee Simmons presented bids opened May 26 for the manganese filtration project. Engineering reviewers from Woodard & Curran identified Linder Construction, Inc. as the apparent low bidder at $6,819,000 and said the low bid fell near the low end of the engineer’s opinion of probable cost. Engineers and trustees discussed change-order risk, noting a roughly 5% spread between bidders and that many change orders arise only if unexpected conditions appear during excavation. Woodard & Curran emphasized typical safeguards: verifying insurance and a detailed schedule of values before payment and recommending a resident inspector during construction.

On the Galina Road raw-water main, trustees approved a contract with Woodard & Curran for design, survey and construction oversight totaling approximately $76,000 ($35,000 for core design tasks, $11,000 for topographical survey, and additional oversight fees). The project would replace roughly 1,200 linear feet of 12-inch raw-water main and ties into a congressionally directed grant of about $990,000; staff said that grant must be used on a Route 29–adjacent project and that connecting the village-owned raw main to the Route 29 corridor made the project eligible.

Jim Revard and Sam Weeden Benner of Woodard & Curran answered technical questions from trustees about contingencies, mobilization differences in bids, and construction oversight. Trustees heard that the village had secured a favorable IEPA funding package for related water-treatment investments (principal forgiveness and low-interest loan portions were described) and that staff would submit required documents to IEPA by the June 10 deadline to finalize the loan agreement by month’s end.

What’s next: staff will issue a notice of intent to award to the selected bidder for the filtration plant, obtain required insurance and documentation, and proceed with IEPA documentation and construction-permit steps for the raw-water-main replacement and filtration plant.