Ticonderoga board names airport committee, hears permit and apron plans

Ticonderoga Town Board · March 14, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Board approved appointments to the airport committee and discussed a phase-one plan including a wetland permit, transformer relocation by National Grid and timing coordination so hangar construction and fence removal can proceed in spring.

The Ticonderoga Town Board approved a resolution appointing members to the towns airport committee and heard an update on airport site work and coordination with utility providers.

The supervisor said a wetland permit had been signed that clears a key environmental hurdle, National Grid intends to relocate an existing transformer from the apron area toward the perimeter to accommodate a future hangar, and core sampling and design work are under way. The supervisor said the town will coordinate with Essex County Department of Public Works and project contractors so fence removal and hangar construction can be completed efficiently.

The board read and approved a resolution naming committee members (chair, vice chair and several members); the resolution passed by voice vote. No roll-call vote totals were recorded in the transcript.

Why it matters: Relocating utility equipment and clearing wetland issues are prerequisites for apron expansion and new hangar construction; timely coordination with National Grid and contractors affects the schedule, staging and potential temporary access impacts for airport users.