Chester says most ARPA projects are closing; public works garage remains largest open item

Chester Budget and Finance Committee · June 1, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The CFO reported Chester has spent about half of its ~$30 million ARPA allocation with 19 projects complete and several targeted to finish by Sept. 30; the public works garage and the public works building remain the largest outstanding items.

At the June 1 Budget & Finance meeting, CFO Richard Troutman gave an ARPA status report that showed the city has closed 19 projects and has nine projects slated to finish by the Sept. 30 near-term target.

"We were awarded a little over $30 million. It has to be spent by the end of this year," Troutman said, adding that roughly $2.5 million from that cohort must be spent in the immediate period to meet documentation and audit deadlines.

Troutman identified several specific items: a planned public works building project with a budget of roughly $8 million (with roughly half slated to be spent through October and the remainder via non‑ARPA funds), a Sun Village playground pavilion (about $300,000 remaining) expected to finish in July, a network upgrade with about $65,000 left, and a fire ladder truck scheduled for delivery at the end of September or early October.

He said the city engaged UHY Advisors to monitor ARPA compliance; the city budgeted $275,000 for that work and has spent roughly $225,000 to date.

Committee members pressed for faster closeout of remaining projects; Troutman said staff and the chief are "all over people to get these projects closed out as fast as possible, doing it right."