Directors split 2-2 on amended Tract 18806 water plans; original contract remains
Summary
The Board voted on amended plans for the Tract 18806 water construction contract (1,620 linear feet of water line for 18 lots in Erwin Lake); the 2-2 split (Rowe and J. Rowe yes; Russo and Walsh no) failed the motion, leaving the original May 5, 2025 contract in place.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
The Big Bear City Community Services District Board considered contractor-proposed amendments to the water construction contract for Tract 18806 at its July 7, 2025 meeting and voted 2-2, resulting in the motion’s failure and leaving the original contract adopted May 5, 2025 unchanged.
General Manager Glenn Jacklin summarized the background: the May 5 agreement had approved 1,620 linear feet of water line to serve 18 new lots in the Erwin Lake area. The contractor’s revised plans proposed removing three fire hydrants, adding two dead-end blow-offs and one drop section blow-off, and reconfiguring the remaining hydrants. Jacklin and staff answered Board questions about those changes.
Director Bob Rowe moved to approve the amended plans; Director JoKay Rowe seconded. The Board recorded votes: Bob Rowe and JoKay Rowe voted yes; President John Russo and Director Larry Walsh voted no. With two yes and two no votes and one member absent the motion did not pass. Meeting minutes note the original contract remains in force.
The Board did not direct further study or amendments at the meeting; staff did not present a revised cost estimate or implementation timetable during public session.