Village extends battery‑storage moratorium as board finalizes draft rules
Summary
Trustees voted to extend the local moratorium on battery energy storage systems (BESS) through November while staff finalizes draft legislation; public commenters raised concerns about school solar carports and asked for a school liaison.
Get email alerts on the Land Use Bess topic
No spam. Unsubscribe anytime.
The Village Board opened a public hearing on a proposed extension of the village’s moratorium on battery energy storage systems (BESS) and later voted to adopt the extension. Staff described the extension as a pause while the board and counsel complete a draft law, with an expected target for a proposed draft in September.
Trustees said the moratorium extension is procedural—intended to preserve the village’s ability to study zoning and safety issues before accepting or approving new BESS applications. Board members noted that there were no active BESS applications pending at the time of the hearing.
Residents asked how the moratorium affects school solar carport projects. One commenter said the district had built solar carports that store energy and asked for a school liaison to coordinate village and school work. Village staff said they had issued stop‑work orders on two school solar sites earlier in the meeting and described the matter as a legal issue under discussion with the superintendent.
After discussion the board moved to close the hearing, and then moved to adopt the moratorium extension (PLLO 02025). The motion passed on voice vote.
The extension leaves in place the village’s temporary prohibition on accepting or acting on new BESS permit applications while staff completes the draft law and advisory materials. Board members said they will revisit the draft law when counsel and staff return with a completed proposal.