Caln Township approves three contractor payments for bridge and farmhouse repairs, unanimous votes
Summary
The board approved three contractor payment applications — bridge repair payment application #1 ($44,878.50), release of retainage ($4,986.50), and a final roof repair payment ($19,631.60) — each motion passed 5–0.
Get email alerts on the Municipal Finance topic
No spam. Unsubscribe anytime.
The Caln Township Board of Commissioners approved three contractor payment applications during its meeting.
• Calumetian House Road bridge repairs: Payment application #1 in the amount of $44,878.50 was approved after the engineer reported repairs were complete and the bridge reopened Oct. 17. Motion moved by Commissioner Evans, seconded by Commissioner Kennedy; vote: 5–0.
• Calumetian House Road bridge retainage: Release of the final retainage and final payment of $4,986.50 was approved; the contractor had no punch‑list items. Motion moved by Commissioner Young, seconded by Commissioner Evans; vote: 5–0.
• Ackman (Spectrum) Davis Farm roof repair: Final payment application #2 in the amount of $19,631.60 was approved (moved by Commissioner Evans, seconded by Commissioner Kennedy); vote: 5–0.
Each motion passed unanimously. No further action was recorded on those projects at the meeting.