Authority hears progress report on Dutch John water treatment plant and Daggett County Health & Business Community Center

Daggett County Municipal Building Authority · June 2, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Members heard updates that the Dutch John water treatment plant is progressing — with software installation and roof work underway and an expected completion in late June or early July — and that the Daggett County Health & Business Community Center is making progress but has no firm occupancy date.

At the June 2, 2026 meeting of the Daggett County Municipal Building Authority, the Chair noted that a Sunrise representative (identified in the transcript as Jeff McCarty) was on the call but had little to add for the Authority.

A Committee member reported that work on the Dutch John water treatment plant continues: staff are installing software to enable remote operation, roof work on the older building is underway, and crews plan to remove the old treatment system once the new plant is fully operational. The Committee member said, “Hopefully, by the end of this month or first part of July, that should be completed in the building.”

The Chair and a Committee member also updated the body on the Daggett County Health & Business Community Center, saying construction is making progress but that a firm completion or occupancy date is not yet available.

The meeting packet and discussion clarified that a $52,000 line item in the invoice register is lease revenue tied to the water treatment plant project (split in the register as $45,000 and $7,002.35). The Authority noted a construction meeting for the community center on Thursday at 10:00 a.m. for interested members.

No votes were taken on the projects themselves; the updates were informational and the Chair closed that portion of the agenda before moving on to financial business.