Lyter Land Development approval delayed pending NPDES permit
Summary
Council granted a 30‑day extension for the Lyter Land Development; borough solicitor advised the Planning Commission that final approval cannot occur until an NPDES permit is issued.
Get email alerts on the Permits topic
No spam. Unsubscribe anytime.
The commission noted that Council granted the Lyter Land Development a 30‑day extension on Jan. 5. The borough solicitor advised that the project cannot receive final approval until the National Pollutant Discharge Elimination System (NPDES) permit has been issued, delaying closure of the review process.
No further details on the permit status, timelines or permit‑holder obligations appear in the minutes. The commission recorded the extension and the solicitor’s guidance as a constraint on final action.