Commissioners approve contractor price increase for road‑construction material
Summary
The court approved a price increase request from MEC Logistics LLC for grade‑three aggregate used in chip sealing after staff said MEC's supplier (Brontex) raised prices by about $5.50 per ton; estimated added cost to the county is roughly $14,000 if applied to remaining material needs.
Get email alerts on the Infrastructure Procurement topic
No spam. Unsubscribe anytime.
Washington County accepted a request from MEC Logistics LLC to adjust contract pricing for road construction materials after staff reported a price increase from MEC’s upstream supplier, Brontex.
Mr. Stokes told the court the county has acquired about 2,268 tons of an estimated 5,447 tons needed for the year; Brontex informed MEC that it was raising its price by roughly $5.50 per ton because of higher fuel and supply costs and MEC asked the county to allow the passed‑through increase. Stokes said the county verified the vendor's information and estimated that, if approved and fully passed to the remaining material needs (approx. 3,179 tons), the increase could add roughly $14,000 to the road‑materials line item for the year.
Commissioners discussed the procurement process and the county’s practice of contacting alternate awardees if a contractor seeks a price increase; the court approved the requested increase by voice vote.
Stokes said staff will continue to monitor commodity pricing and noted there is a chance of additional increases depending on market conditions.