City staff reports progress on sewer, water and drainage projects and $8.3M in active grants

City of Tomball City Council · June 1, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The city gave a March 31, 2026 CIP and grant update: several infrastructure projects are midstream (FM2920 lift station ~50% complete; Baker Drive water plant ~90% with July estimated substantial completion), two projects finished under budget, and staff reported six active grants (~$8.3M) and 15 pending applications (~$50.6M).

City staff presented the capital improvement project and grant quarterly update as of March 31, 2026, outlining progress across water, sewer and drainage projects and summarizing grant activity. "The FM2920 lift station improvements phase one is progressing approximately 50% complete," staff reported, and the Baker Drive Water Plant was described as at "90% completion" with substantial completion expected in mid-July.

Staff said the Eastwater treatment plant had advanced from about 35% to roughly 45–50% completion since the last report, the south wastewater expansion was nearing 30% and remains scheduled for a December 2027 finish, and two projects (alley amenities and a 16-inch water line on HubSmith Road) finished this quarter under budget.

On grants, staff said the city had "six total active grants with approximately $8.3 million in funding with 1.1 spent to date" and had 15 pending applications totaling about $50.6 million. The presentation identified several active and pending grants by project (M18/Lizzy Lane drainage, fire-truck and police vehicle grants, playground replacement, and South Pimen and Tempkin funding) and noted that some awards will move from pending to active upon execution of agreements.

Council asked clarifying questions about design approvals, TxDOT reviews and timelines. No formal vote was required on the update; council accepted the report and staff will return with project-specific details as needed.