Collierville awards $303,645 Walnut Street drainage contract; road closed ~120 days during construction

Board of Mayor and Aldermen, Town of Collierville · May 11, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved a $303,645.40 unit-price contract to the lowest responsive bidder (NScore) for Walnut Street drainage improvements; staff expects roughly 120 calendar days for construction and $600/day liquidated damages for delay.

Town Engineer Dale Perryman presented the Walnut Street drainage-improvement project and recommended awarding the construction contract to the lowest responsive bidder, NScore, at $303,645.40.

Perryman said the work — located on Walnut Street between Mulberry Street and North Harlot Street — includes approximately 440 feet of drainage pipe (18–42 inches), eight drainage structures, asphalt patching and traffic control. Construction will require a full closure of Walnut Street during work for approximately 120 calendar days; liquidated damages are set at $600 per day. The project could not proceed earlier because downstream drainage phases needed completion; those downstream phases were finished in December 2025, allowing this project to start.

Seven vendors requested plans; four bids were received. Perryman said the contract is a unit-price arrangement and that remaining funds will be returned to the appropriate account when the project is completed. The board approved the award by roll call.