Commissioners approve $25.7 million Phase 1 BOT agreement with Avenew for West Lafayette infrastructure project
Summary
Tippecanoe County commissioners voted to award a Build‑Operate‑Transfer transaction to Avenew, Inc., approving Phase 1 with a guaranteed maximum price of $25,692,000; Phase 2 will proceed after a future public hearing, the county attorney said.
Get email alerts on the Infrastructure Bot topic
No spam. Unsubscribe anytime.
The Tippecanoe County Board of Commissioners voted May 18 to award a Build‑Operate‑Transfer (BOT) transaction for the Tippecanoe County–West Lafayette infrastructure project to Avenew, Inc. Attorney Doug Masson told the board the firm was selected after advertised proposals for qualifications were reviewed.
The county recorded a Phase 1 guaranteed maximum price of $25,692,000; Masson said Phase 2 remains a work in progress and will require a future public hearing and resolution. Following the hearing, Commissioner David S. Byers moved to approve Resolution 2026‑15‑CM awarding the BOT transaction to Avenew; President Tracy A. Brown seconded and the motion carried.
"The BoT process involves prior advertised proposals for qualifications that were reviewed and awarded to the firm Avenew, Inc., for the infrastructure project," Masson said, describing the procurement and the two‑phase approach. The resolution before the board documented the Phase 1 GMP and set Phase 2 for later public review.
The vote completed the formal award; the transcript does not record a roll‑call tally beyond the recorded motion and second. County staff did not present a timeline for construction start or an itemized Phase 1 scope in the meeting record; Masson indicated additional public steps for Phase 2 would follow. The board took no additional motions changing the award at the May 18 session.