Hampstead says water pipeline work is on schedule and under budget, completion targeted August 2027

Hampstead Planning and Zoning Commission · May 27, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Town staff told the Hampstead Planning & Zoning Commission the pipeline portion of the town's water system project is on schedule, running below the contracted price and is estimated to be finished by August 2027; treatment-plant grading and sidewalk work remain.

The Hampstead Planning & Zoning Commission heard an update on the town's water system project at its May 27 meeting, during which staff reported the pipeline portion is proceeding on schedule and below the contracted price.

Zoning Administrator said that "the pipeline portion of this project is coming in on time, under time, and also below the contracted price," and that new water mains and accessories are installed while sidewalk reconstruction and site work remain. He said construction trailers are in place on Shiloh Avenue and pre-construction meetings with county grading and settlement-control staff are being scheduled for grading at North Carol Farms and Hampstead Valley, the latter near Chief Sites Park.

Why it matters: the project moves key drinking-water infrastructure forward for multiple neighborhoods while aiming to stay within the contractor's budget. The administrator told commissioners the contractor expects to have "everything totally wrapped up by August of 2027." That timeline covers the pipeline portion; additional work remains for the water treatment plant component.

Commissioners asked questions about staging and access; staff described separate trailers for the pipeline work and for the treatment-plant construction. The update noted that progress meetings indicate the schedule is being met but did not provide a detailed monthly work plan or a firm date for treatment-plant completion.

Next steps: staff will continue coordination with county grading regulators and bring subsequent progress updates to the commission. No formal action or vote was taken on the update.