River Ridge CDD adopts loan amendment and approves $173,367.78 ditch-cleaning contract

River Ridge Community Development District Board of Supervisors · June 25, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

On unanimous votes, the River Ridge CDD board adopted Resolution 2024-05 to amend its Series 2024 Note loan agreement (Synovus Bank) and approved an MRI Construction estimate of $173,367.78 for dry-retention flow-way ditch cleaning adjacent to River Course holes #6–#8; the board said loan proceeds will cover the drainage projects.

The River Ridge Community Development District Board of Supervisors unanimously adopted Resolution 2024-05 on June 25, authorizing an amendment to the use of proceeds from its Improvement Revenue Note, Series 2024, and authorizing a first amendment to the loan agreement with Synovus Bank.

Chuck Adams presented the resolution and described the amendment as allowing revised project scope for use of the Series 2024 Note proceeds. "On MOTION by Mr. Blumenthal and seconded by Mr. Mountford, with all in favor, Resolution 2024-05 ... was adopted," the minutes state.

Immediately afterward, the board approved an MRI Construction, Inc. estimate for dry retention flow-way ditch cleaning adjacent to River Course Hole #6 through #8 in the amount of $173,367.78. Mr. Krebs presented the estimate and addressed scope questions; the minutes record: "On MOTION by Mr. Blumenthal and seconded by Mr. Twombly, with all in favor, the MRI Construction, Inc. Estimate ... in the amount of $173,367.78, was approved." Staff noted loan proceeds will cover the drainage projects and that an irrigation project was included with a 10% contingency.

Votes at a glance: - Resolution 2024-05 (amend Series 2024 Note loan agreement with Synovus Bank): adopted (motion: Blumenthal/Mountford; vote: unanimous). - MRI Construction, Inc. estimate for ditch cleaning ($173,367.78): approved (motion: Blumenthal/Twombly; vote: unanimous).

Why it matters: The approvals authorize using bond/loan proceeds and a contractor to perform drainage-cleaning work the district says is part of the improvement scope, moving the projects toward implementation.

What’s next: Staff will proceed with the ditch-cleaning contract and coordinate funding per the amended loan agreement; related easement work and sketches for longer-term improvements are being prepared by the district engineer.