Clallam County extends Ecology grant term, adds fish‑screen feasibility study for Off‑Channel Reservoir

Clallam County Board of Commissioners · April 6, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

County staff told commissioners they will ask to authorize amendment of a Department of Ecology grant to extend the term to July 31, 2027 and add a feasibility study to evaluate installing a fish screen at the HID diversion; staff said design is paused for a 30% design reset and that construction funding for the reservoir is not yet secured.

County staff briefed the board on a contract amendment with the Washington State Department of Ecology for the Dungeness Off‑Channel Reservoir project. The amendment would extend the Ecology grant term to July 31, 2027, expand the scope to include a feasibility study for a point‑of‑diversion fish screen at the HID diversion and cover updated design tasks tied to a 30% design reset.

Staff noted minor typographical errors in the draft amendment (comma placement and numeric formatting caused by the document system) and described the signature process: county staff will receive a DocuSign link and the board can authorize the chair to sign next Tuesday. Commissioners indicated they were comfortable authorizing signature even if Ecology’s signature page may arrive later.

On funding, staff said design funding for upgrading and improvements is largely secured, but construction funding for building the reservoir itself has not been secured. The county is negotiating contract language with NRCS (for a major conveyance pipeline) and is tracking applications to other partners: Washington State Department of Fish and Wildlife has applied for a state grant to help fund construction of the point of diversion; if those awards do not materialize the county will pursue alternatives through the reservoir work group.

Staff expects to return to the board with the 30% design reset and associated consultant report within weeks to brief commissioners on the design review outcome.