Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Transportation topic

No spam. Unsubscribe anytime.

Council approves change to Joint Highway Committee canal crossing project amid funding constraints

Price City Council · August 13, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Price City approved a request to change the Joint Highway Committee canal crossing project to a single crossing at Carbon Avenue, reducing scope because of funding limits; total project cost was reported at $958,505 with a city share of $233,409 (24%).

Price City Council voted Aug. 13 to request a scope change to the Joint Highway Committee canal crossing replacement project, approving a reduction from two crossings to a single crossing at Carbon Avenue because of current funding constraints.

Council Member Miller moved the request and Council Member Chrisman seconded. The chair read the project total as $958,505 and noted the city's portion would be $233,409, described in the meeting as roughly 24% of the project. Discussion referenced an engineering study that prioritized Carbon Avenue as the highest‑priority crossing.

The council approved the motion by voice vote.

Next steps: The item will be forwarded to the Joint Highway Committee for processing under the revised scope and the council will follow up on funding allocation and scheduling as that regional committee acts.