Council directs staff to accept $1.5M TIB grant and proceed with Central Way raised bike-lane alternative

Kirkland City Council · June 3, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

After receiving a $1.5 million Transportation Improvement Board grant, Kirkland council directed staff (6-0) to pursue Alternative 2 — an expanded raised bike lane and wider sidewalk — and to fund the local match largely from TBD contingency and reprioritized CIP items.

The City of Kirkland received a $1.5 million Transportation Improvement Board Complete Streets grant for Central Way bike-lane improvements, and on June 2 the council directed staff to proceed with the project and the recommended design, Alternative 2.

Public Works project manager Jessica Clemens described four options considered during a prior study session. Alternative 2 proposes a raised 6-foot bike lane and an 8-foot sidewalk, including a small encroachment on the adjacent park requiring a modest fence shift (maximum 3.7 feet at one corner). Staff estimated the total project budget at about $3.98 million (transportation share roughly $2.9 million; park share about $1.1 million).

Clemens and councilors discussed scope and cost drivers: slope work, retaining walls, fence and netting replacement at the ball field, upgraded lighting, utilities and soil-cell planting systems for long-term tree health. Council member Pascoe questioned per-foot cost; staff noted those additional elements drive the price beyond simple pavement.

Staff proposed funding the local match from the Transportation Benefit District contingency (current balance approximately $4.2 million), repurposed amounts from other CIP projects (some near-term scopes and $300,000 from a preservation project) and, if needed, limited REIT reserves. The council asked staff to return with a TBD reconciliation and to preserve higher-priority TBD projects. Council directed staff to accept the grant, advance the design as Alternative 2, and pursue the funding approach described; the motion passed 6-0.

Next steps: staff will return with CIP updates, a fiscal note for approval, and any needed refinements to scope or funding.