After an extensive technical discussion on animal welfare, staff recommended a contract with Core Construction at a guaranteed maximum price of $429,741 to add air conditioning and LED lighting to the city animal-control kennel; the council voted to table the item pending further analysis of alternatives including modern evaporative cooling and facility expansion.
Get email alerts on the Animal Welfare And Capital Projects topic
No spam. Unsubscribe anytime.
Casa Grande — The City Council on June 1 tabled a proposed contract to install air conditioning and LED lighting at the city’s animal-control kennel, after council members questioned the $429,741 guaranteed maximum price and urged staff to investigate alternatives and facility expansion options.
Staff presentation: A lieutenant in charge of animal-control explained the project scope and said Core Construction — which originally built the kennel in 2009 — submitted a proposal for an upgrade that would replace evaporative coolers with dedicated air-conditioning units and add LED lighting to address heat, animal welfare and staff working conditions. He cited the guaranteed maximum price of $429,741 and explained that updated animal-care AC systems include higher air recirculation rates and quarantined rooms to reduce disease transmission.
Council debate: Several council members pressed whether the money might be better spent expanding kennel capacity or upgrading evaporative cooling systems rather than installing AC, arguing evaporative cooling flushes air out of the building and can be cost-effective in Arizona’s climate. The lieutenant and project staff responded that modern AC solutions are often recommended for new builds and that certain recirculation features are important to disease control. One council member noted staffing and volunteer exposure to heat while working long shifts.
Outcome: Council member Sean moved to table the item to allow staff time to study alternatives, including updated evaporative cooling options, expansion needs, and a needs assessment. The motion passed with all but one council member voting in favor; the record shows one ‘no’ vote and the rest in favor. Mayor Fitzgibbons said staff will follow up with the city manager and return to council with additional information.
Why it matters: Staff said the kennel often operates at capacity and that heat creates welfare and occupational-health concerns for animals and staff. Council members emphasized fiscal prudence and asked staff to return with options that balance animal welfare and long-term operational value.
Ending: The item was tabled for further study; no contract was authorized. Staff indicated the proposal’s pricing was time-limited (15 days) and the city may need to refresh the proposal if the council changes scope or returns to it later.