Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Construction topic
No spam. Unsubscribe anytime.
Committee says Wakefield school construction on track as finishes and site work proceed
Summary
Project committee reported progress on exterior site work, façade and interior finishes for the new Wakefield high-school building, set timelines for locker-room epoxy floors and terrace/terrazzo work, and flagged retainage and utility coordination to enable summer system hookups.
Get email alerts on the Construction topic
No spam. Unsubscribe anytime.
The committee overseeing the Wakefield school project received an update on construction progress and timeline, with the committee chair describing substantial exterior and interior advances.
"We are in the process of doing exterior site work on the amphitheater and AE courtyard site," the chair said, listing ramps, loading-dock work, shade-structure foundations and stone-bench installation. The chair said contractors have completed most masonry veneer and that interior finishes—classroom flooring, doors and sidelights, epoxy floors in science rooms and locker-room preparations—are moving toward multi-week completion milestones.
Designers told the panel that courts, batting cages and acoustic panels in the gym are nearly complete and that crews will begin epoxy flooring in locker rooms the week of June 15. A terrazzo mock-up in the front meeting space is under review with “some homework” to address comments before bridge-area terrazzo proceeds.
On contract closeout and payments, committee members debated retainage timing. One member noted common practice of partial retainage releases later in the fall but warned against returning so much money that contractors lose incentive to finish punch-list items. As context, the Century contract was described as a multi-million-dollar job, and holdback discussions referenced typical reductions in the 50–55% range as a mid-point for negotiation.
The committee also identified several outstanding coordination points: confirming lead times for specialty items (lighting fixtures, Musco field-lights), finalizing the schedule for WCAT’s equipment installation and confirming who will sign off on stormwater elements tied to a potential site-plan amendment. The chair asked the design and project teams to circulate final design packages and change-order documents one week before the June 18 full meeting so members can review before votes or approvals.
The committee approved the Hall of Fame layout and asked school staff to confirm the content for display cases; the athletic display decision was described as a final-layout approval rather than a programmatic policy change.
What happens next: the working group will deliver final layouts and change-order paperwork ahead of the June 18 meeting and bring a retainage plan forward in the fall to balance progress payments with warranty and punch-list protections.

