Oliver Springs utility staff: no TDEC violations remain, pumping steady and pipeline projects underway
Summary
Staff told the board on June 3 that the plant is pumping about 650–660 gallons per minute, the recent TDEC performance-audit issue (an incubator temperature) was corrected with a new incubator, there were no collection-system overflows for March–May, and several water-line projects have been completed or are starting soon.
Get email alerts on the Operations topic
No spam. Unsubscribe anytime.
Utility staff briefed the Town of Oliver Springs Water Board on operations, compliance and capital work during the June 3 meeting.
The chair reported an improvement in the town’s water loss rate: "Looks like our water loss rate's down about 45%," the chair said. Staff confirmed the distribution system has seen no collection-system overflows for March through May, a notable change after historical overflow problems.
Staff reported that the treatment plant is producing roughly 650–660 gallons per minute and that recent monthly water sales were about 8,590,000 gallons; staff estimated that generated roughly $123,000 for the month compared with a budget target near $115,000. Staff also told the board that TDEC conducted a performance audit in March, identified one minor violation (a sample incubator temperature outside allowable limits), and that the town purchased a new incubator to clear the issue.
On capital work, staff said the 10-inch water line on Ritchie Drive (CDBG-funded) has been completed and closed out; work has started or will start soon on projects including a 6-inch line on Rohn Street (ARC project), an 8-inch relocation on West Tri County Boulevard, and repair/payment work on Airport Road pending contractor billing. Upcoming in-house projects listed included Ridgeview Drive and Willow Springs.
Staff also described operational changes affecting meters and telemetry: the town plans to order antennas for additional collectors rather than install costly tower antennas, and the customer portal is available for usage history and ACH/autopay signups. Staff reminded customers of the new leak-insurance procedure and the two-claim allowance under the new policy.
Staff said state-required consumer-notification steps (CCR posting and newspaper notice) are scheduled in June. The board had no further substantive comments and moved on to the budget discussion.