New Windsor board approves wastewater/water contract change orders and files DEC permit for PFAS project
Summary
The board received NYSDEC permit documents for the Butterhill PFAS treatment project (permit authorizes up to 7,027,200 gpd) and authorized multiple change orders for the Resideo's Lane wastewater treatment plant phase‑1 work, increasing contract allowances to address plan revisions.
Get email alerts on the Wastewater And Water Projects topic
No spam. Unsubscribe anytime.
The Town Board of New Windsor received and filed state correspondence related to the Butterhill Wells PFAS treatment improvement project and authorized contract change orders for the wastewater treatment plant upgrade.
Supervisor Steve Beddetti reported receiving written notice from the New York State Office of Parks, Recreation and Historic Preservation that no listed archaeological or historic resources will be impacted by the Butterhill Wells/PFAS treatment improvement project. The board also received a New York State Department of Environmental Conservation permit (Permit ID 3-3348-00001) that authorizes the New Windsor consolidated water system to withdraw up to 7,027,200 gallons per day from the permitted source.
Separately, the board authorized a change order with American Electric (electrical contractor) to incorporate plan revisions and clarifications provided by MHE Engineering dated April 6, 2026, approving an increase of $41,006 plus replenishment of the electrical construction allowance of $20,000 for a total additional $61,006; the action is subject to town attorney and town engineer approval. The board also authorized Change Order No. 3 with Baron Construction Group, the general contractor for Resideo's Lane wastewater treatment plant phase 1, approving $231,995 in plan revisions and replenishment of the general construction allowance of $50,000 (total increase $281,995), also subject to attorney and engineer approval.
Supervisor Beddetti said the additional funds are being taken from contingency already built into phase 1 and described routine inspections that prompted recommended items. The motions passed on roll call.
Implementation notes: the change orders were authorized to allow the contractor to proceed with clarified plans; both change orders are conditioned on final form and town engineer approval before execution.