Board approves 5% contingency after $133,000 in change orders on River Road transmission main
Summary
Staff reported three unforeseen underground construction issues on the River Road transmission main — unmarked steel casing tap, relocated sewer force main bury depth and an unmarked Verizon conduit — totaling about $133,000 on a $10 million contract; the board gave consensus to a 5% contingency (~$550,000) from cash reserves.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Prince George County utilities staff told the board that contractor change orders on the River Road transmission main project have produced a request of roughly $133,000 on a $10 million contract — about 1.2% — and asked for board consensus to establish a 5% contingency to cover additional, near‑term change orders.
Utilities staff described three issues found in the ground that required extra work: cutting a 30‑inch steel casing to tap an existing water line (about $72,000), additional depth and excavation because a sewer force main location was not where the drawings indicated (about $32,000), and an unmarked Verizon conduit struck during jacking across Scotland Road that required Verizon repairs (about $30,000). "This is about a 1.2% change order on a $10,000,000 project," staff said.
Because the contract contained no contingency, staff requested consensus to appropriate a contingency of about 5% of the contract amount (roughly $550,000) from cash reserves to cover the current change order and potential near‑term additional items; any future change orders would still be brought to the board for review. The board gave consensus on the 5% contingency and directed staff to return with the formal appropriation at a future meeting.
Staff emphasized that any change orders above thresholds would be reported and would appear on the board's agenda for action as required.