Commissioners approve debris-monitoring contractor; cancel and reissue debris-removal RFP pending scope and permitting clarity
Summary
A review panel recommended a debris-monitoring contractor to meet FEMA reimbursement requirements; commissioners approved awarding monitoring services and voted to cancel and reissue the debris-removal RFP after reviewers found the removal scope and permitting requirements unclear.
Get email alerts on the Disaster Recovery topic
No spam. Unsubscribe anytime.
Commissioners voted to appoint a contractor to provide disaster-debris monitoring services, a function FEMA requires for reimbursement of debris-removal work. The review panel presented scoring and tabulation sheets from multiple proposals and recommended a vendor; during the meeting commissioners approved the board motion to engage the monitoring contractor. Commissioners emphasized that monitoring is essential to preserve reimbursement eligibility once a disaster declaration is in place.
On the debris-removal and disposal procurement, the review panel recommended canceling and reissuing the RFP after determining that the existing solicitation did not adequately define the potential scope of work, permitting requirements or acceptable downsizing options (including leaving some debris in waterways when permit agencies determine that is appropriate). Commissioners voted to cancel the current debris-removal RFP and directed staff to reissue a more specific solicitation once the county has more clarity on damage extent, permitting outcomes and any disaster-declaration reimbursement parameters.