Supervisors approve Turner Construction pay applications for courthouse, evidence storage, and other county projects

Dallas County Board of Supervisors · June 2, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved Turner Construction pay applications for the courthouse renovation ($451,574.35) and the evidence storage/firing range ($1,663,973.88), and approved a smaller pay application for the Secondary Roads addition ($61,394) and a certificate of substantial completion for that project.

Dallas County supervisors approved multiple construction pay applications and received project updates at their June 2 meeting.

Courthouse renovation: Christopher Orth of Farnsworth Group reported the renovation is about 69% complete, with excavation, waterproofing, framing and finish work in progress including millwork for a new jury courtroom. The board approved Turner's pay application number 14 in the amount of $451,574.35 for work completed through May 31, 2026.

Evidence storage and firing range: Staff said site grading, installation of ballistic baffles, HVAC and electrical rough-in work are underway and the project is approximately 79% complete. The board approved Turner's pay application number 15 in the amount of $1,663,973.88 for work through May 31, 2026; the payment included stored material costs and equipment deliveries associated with the firing range.

Secondary Roads addition and garage: County staff reported the county moved into the facility in late April and most punch-list items are being finalized. The board approved pay application number 18 in the amount of $61,394, and subsequently approved a certificate of substantial completion for that project and authorized the chair to sign.

Contingency and allowance balances were reported for the projects (courthouse contingency remaining $135,483; evidence storage contingency ~$177,559 and allowances ~$276,958; figures presented in the project slides). Supervisors moved and approved each pay application by motion and voice vote at the meeting.

What’s next: staff will continue punch-list work and return with contract amendment requests or reimbursement resolutions as needed; the county will process the approved pay applications for payment.