Daniels County signs notice to proceed for Cold Creek Bridge construction
Summary
The board reviewed contract documents for the Cold Creek Bridge project, discussed contract line items and schedule, and unanimously approved signing the contractor's notice to proceed with demolition and construction scheduled to begin the week of Aug. 5.
Get email alerts on the Infrastructure Bridges topic
No spam. Unsubscribe anytime.
Daniels County commissioners reviewed the Cold Creek Bridge construction contract and authorized staff to sign the notice to proceed, the board recorded.
Commissioners examined contract pages covering the notice to proceed, contract price components (noting a structure payment already made and separate surface/base items), and the contractor's proposed schedule. County discussion referenced a total contract package near $1.8 million when structure and surfacing were combined; commissioners noted the contractor planned to begin demolition the week of Aug. 5.
After discussion, a motion to sign the notice to proceed was made and seconded; the vote was recorded as unanimous and the board authorized executing the contract paperwork.
The county will continue coordination with project staff for preconstruction and will monitor the contractor's mobilization and guardrail/approach requirements.