Strafford County says contractor Hutter will produce warming-center plans; AOT not required
Summary
County officials reported Hutter was awarded the warming-center contract and has teamed with Warren Street to produce plan sets in a 6–8 week lead time; staff said an alteration-of-terrain permit is not required, which may shorten the schedule. A separate women’s-shelter contract was also discussed as having been awarded after an executive session.
Get email alerts on the Warming Center topic
No spam. Unsubscribe anytime.
Strafford County officials reported that a contract for a new warming center was awarded to Hutter and that Hutter has partnered with Warren Street to develop construction plans based on the county’s concept. Officials said Warren Street indicated a 6–8 week lead time to produce a set of plans suitable for review by inspectors.
Board members said the contractor expects the project schedule to be shorter than originally presented because the state advised that an alteration-of-terrain (AOT) permit will not be required. County staff said that removal of the AOT requirement should speed the timeline to construction, but they did not provide a revised construction completion date at the meeting.
Members also discussed a women’s-shelter contract that staff said was awarded following an executive session on the 30th; officials told the meeting that contract negotiations took place in nonpublic session and that no further approvals from the delegation were required. The public question about the shelter award prompted the board to confirm the award date and negotiation history but the record provided at the meeting did not include the full contract text or dollar amount.
Board members said Hutter has committed to providing plan documents in six to eight weeks and indicated it expects to have plan sets to the county within that window; the contractor also indicated a target to have construction completed by November in earlier materials, though meeting discussion focused on near-term design deliverables. County staff emphasized they have not yet received all final documents and will post materials on the county website when available.
The meeting record shows no public vote on the contract at this session; participants said the award was made following an earlier executive session. The board moved into a nonpublic session later in the agenda for personnel and contract negotiations.